Title:

Rehabilitate Waterfront Dock

Location:

Fort Sumter, South Carolina

Owner:

National Park Service

General Contractor/Client:

Terra Constructs

Designer:

GWWO Architects

Project Start Date:

September 2020

Project Completion Date:

October 2021

Project Overview:

The National Park Service selected Terra Constructs to perform construction requirements necessary to extend the service life of the pier.

The existing pier required structural upgrades and improvements related installation of new steel piles, fendering, removal and reinstallation of riprap, repairs to concrete piles and pile caps, pile jacketing, concrete deck replacement, deck repairs, electrical service upgrades, and dock lighting.

Purpose:

The pier has experienced damage and deterioration related to weather events, age, and increased ferry boat service schedules. The primary purpose of the project is installation of new four (4) steel pile systems with rubber fendering to eliminate direct transfer of energy from the boats to the dock when approaching and leaving the dock. Electrical systems were upgraded and designed to prevent saltwater intrusion during a significant storm or tidal event.

Challenges:

  • Design challenges to accommodate Ferry Boats
  • Tidal fluctuations and inclement weather
  • Protection and accommodation of Park guests
  • Coordination of construction sequencing with Ferry Boats

Solutions:

Partnered with the client, designer, and ferry boat captains to develop a practical and cost-effective solutions to ensure mooring and access requirements were achieved.

  • Coordinated schedule activities to accommodate tidal fluctuations and provided weekly updates to the client
  • Held multiple coordination meetings with the client and ferry service to establish and implement a comprehensive safety protection plan for the Park guests.
  • Held multiple coordination meetings with the client and ferry Captain’s to establish clear communications and requirements for the Contractor as necessary to minimize disruption to the Park.

Outcome:

Terra delivered the project on schedule and on budget.